Computer Shutdown Sequence

Only a few manual actions are needed after an automated shutdown sequence has occurred.

Manual Actions needed AFTER the auto-shutdown script runs:

  1. Mountain staff need to shutdown the AO TSS power (TO, Mountain Mgr.)
  2. Mountain staff need to power down jet.mountain.lbto.org located in AUX control room

Core Network and Computer Room Electricity

ONLY do the following if the power is completely down!

  1. Turn off the REAR switches to the three power supplies on core-b (Rear R2 CRA, U1-U21).
    Core-b power supplies are labeled "4","5","6".
    Core_B-sm.jpg

  2. Turn off main circuit breaker located in CRA circuit breaker panel PP22-UPS-1 (Right wall CRA)
    PP22-UPS-1-sm.jpgPP22-UPS-1Breakers-sm.jpg

    1 Turn off main circuit breaker located in CRB in circuit breaker panel PP22-UPS-2 (located on wall near MODS rack, CRB).
    PP22-UPS-2-sm.jpg PP22-UPS-2Breakers-sm.jpg

I Attachment Action Size Date Who Comment
Core_B-sm.jpgjpg Core_B-sm.jpg manage 80 K 07 Jul 2017 - 20:21 UnknownUser Power supply/breaker box pictures, CRA and CRB
PP22-UPS-1-sm.jpgjpg PP22-UPS-1-sm.jpg manage 113 K 07 Jul 2017 - 20:21 UnknownUser Power supply/breaker box pictures, CRA and CRB
PP22-UPS-1Breakers-sm.jpgjpg PP22-UPS-1Breakers-sm.jpg manage 109 K 07 Jul 2017 - 20:21 UnknownUser Power supply/breaker box pictures, CRA and CRB
PP22-UPS-2-sm.jpgjpg PP22-UPS-2-sm.jpg manage 37 K 07 Jul 2017 - 20:21 UnknownUser Power supply/breaker box pictures, CRA and CRB
PP22-UPS-2Breakers-sm.jpgjpg PP22-UPS-2Breakers-sm.jpg manage 143 K 07 Jul 2017 - 20:21 UnknownUser Power supply/breaker box pictures, CRA and CRB
Topic revision: r8 - 10 Jul 2017, DouglasSummers
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Foswiki? Send feedback