SV summit tasks 17,18,19 Jan 2023

  1. Verify on-site the SV integration procedure criticalities, from unloading crates to installation on LBTI DX bracket, particularly clear passage of SV cart along route from clean room to dome.
  2. Verify current status of LBTI DX bracket with SOUL: measure clearances for SV and verify absence of criticalities.
  3. Inspect current status of LBTI DX inboard electronics rack, where SV electronics are to be installed.
  4. Inspect Forerunner, disassemble filter and measure for possible future substitution.
Topic revision: r1 - 10 Jan 2023, AlbertConrad