Software Progress Report May 2009

AdOpt Software

  • The last version of MsgD has been thoroughly tested and put in use in the Solar Tower lab.
  • More work on startup procedures to enhance reliability and safety
  • More work on Arbitrators (WFS and AdSec) and the related GUIs (referred to as WFS Control GUI and AdSec Control GUI). This part of the activity is desribed in more details in the general montly reportby S. Esposito.
  • AdSec Mirror Diagnostic GUI development still in progress

AOS

  • Tests of a preliminary version of the AOS GUI have been started
  • Engineering modes commands related to the hexapod have been revised and updated.

Documentation

  • A revision of the documentation for the entire AO Supervisor software has started.

Miscellaneous

  • Some work was needed to verify the configuration of workstations used for the Solar Tower lab tests as well as to set up and configure two Workstations to be used, respectively, for the Interferometer and as spare for the lab activities.