All,
This email is written as follow up on last week's discussions on the LBT672
schedule. This morning we had a meeting at the LBTPO for further
discussions. Below are the main conclusions from the meeting.
TS3 Manufacturing
TS3 delivery from ML scheduled for September 11
TS3 ship date from Arizona is now re-scheduled for October 2
Reference Body #3
RB #3 blank is on order with delivery expected very soon.
Production time at the ML is nominally around 1 month, but there might be other projects competing for resources.
The PO is negotiating with the ML to have RB #3 finished and delivered as soon as possible.