Follow up of the August 2006 meeting

All,

This email is written as follow up on last week's discussions on the LBT672 schedule. This morning we had a meeting at the LBTPO for further discussions. Below are the main conclusions from the meeting.

TS3 Manufacturing

  • TS3 delivery from ML scheduled for September 11
  • TS3 ship date from Arizona is now re-scheduled for October 2

Reference Body #3

  • RB #3 blank is on order with delivery expected very soon.
  • Production time at the ML is nominally around 1 month, but there might be other projects competing for resources.
  • The PO is negotiating with the ML to have RB #3 finished and delivered as soon as possible.

Joar

-- ArmandoRiccardi - 20 Mar 2007