Dear all,
please find below a short summary of the activities of the th related to
the AO system.
People at LBTO:
R. Briguglio
remote support
M.Xompero, A. Puglisi (VNC+Skype)
Summary
Because on unfavourable environmental conditions, the dome has not been opened all night long. Software modifications have been implemented and verified on the system:
* new DSP code has been installed and verified;
* automatic dump of masterdiagnostic process was implemented and tested, to keep trace of system faults;
* system GUIs have been modified to avoid sudden deaths (experienced during the last days);
* modification on system processes done to automatically handle the diagnostic variables;
* software modifications to fix bugs on ADC and rerotator.
At the end of the software tests, the shell has been set as a final verification: the operation was successfully. The shell gap at its rest position is on its nominal range (i.e.24um-39um), the "ear" on shell border is not visible.
ciao
Runa
--
ArmandoRiccardi - 02 Apr 2010