February 2009 Nightly Log files

16-17 February 2009 Lucifer Feb Commissioning Night 11 - Lost to wind and humidity
15-16 February 2009 Lucifer Feb Commissioning Night 10 - Open, with some weather and telescope issues
14-15 February 2009 Lucifer Feb Commissioning Night 9 - Open with a few telescope problems
13-14 February 2009 Lucifer Feb Commissioning Night 8 - Lost to weather and telescope problems
12-13 February 2009 Lucifer Feb Commissioning Night 7 - Open, but poor seeing and telescope problems
11-12 February 2009 Lucifer Feb Commissioning Night 6 - Open but fairly heavy clouds
10-11 February 2009 Lucifer Feb Commissioning Night 5 - Lost to icy enclosure
9-10 February 2009 Lucifer Feb Commissioning Night 4 - Lost to wind and snow
8-9 February 2009 Lucifer Feb Commissioning Night 3 - Lost to wind and snow
7-8 February 2009 Lucifer Feb Commissioning Night 2 - Lost to wind and snow
6-7 February 2009 Lucifer Feb Commissioning Night 1 - Mostly lost to wind
5-6 February 2009 BG Technical observing night 6 - Mostly lost to wind
4-5 February 2009 BG Technical observing night 5 - MCS Engineering plus PSF/GCS testing
3-4 February 2009 BG Technical observing night 4 - MCS Engineering plus Field Aberrations
2-3 February 2009 BG Technical observing night 3 - MCS Engineering plus poor seeing
1-2 February 2009 BG Technical observing night 2 - Testing TCS Build 18
0-1 February 2009 BG Technical observing night 1 - Testing TCS Build 19, some telescope problems

-- DougMiller - 29 Sep 2009