Restart Night #13 - UT 03 Sep 2020

OSA: J. Williams

ISp: E. Solheid

Mtn Manager: J. Schuh

SO/LBTI: J. Power

LBTI: S. Ertel

AO: D. Miller, B. Rothberg (scripting and targets)

NOTE: Split Night between LBTI Restart and AO-SOUL-LUCI - Handover 00:14


Summary:

Based the MGIO revising the status of the site diesel generator to NOT available tonight, LBT will remain closed tonight with closed domed activities possible as long as SX M2 is deployed if off zenith.

Problems:

sire diesel generator unavailable. For telescope and adsec safety, telescope remained closed.

Proposed Plan:

  • First half LBTI
  • If LBTI finishes early:
    • LBC-Bino Checkout
      • collimation
      • super-focus sequnece for both
  • SOUL/LUCI/AO 2nd half
    • System Checkout
      • Diffraction-Limited Verification
        • Verify Bin 1 and Bin 4 (2hrs)
        • Tesct Science Script M52 (1-1.5 hrs)
        • OSCO (0.5 hr)
      • ESM verification
        • Test Science Script M52 (1.5 hr)
      • Poor Weather Contingency
        • ESM Verification (as long as loops can close collect data)
        • Check WFS magntiudes against known magnitudes

Closed dome Plan:

Flexure data collection for LUCI:
  • G150+N375 K / G040+N375 J
  • G150+N180 K / G040+N180 J will need "lamps off" data for G150 K data
  • N180 img
Verify Wavelength

Night Log:

Will obtain some of the more obscure flex comp data sets tonight while we are closed. Testing a few configurations to start. I will start with N1.8 Imaging though

### N1.8+Mirror K
__LUCI1__ LUCI2 EL Comments:___________

0043 0115 0016 0088 90 FlexComp_Calib15.xml
0116 0188 0089 0161 68
0189 0261 0162 0234 46
0262 0334 0235 0307 24

###L1G150_N375K 2.17 Ne,Ar,Xe
###L2G040 AO N375 J 1.3 Ar

LUCI1 LUCI2 EL Comments:___12sec exposures________

0337 0409 0309 0381 24 FlexComp_Calib15_12s.xml
0410 0482 0382 0454 46
0483 0555 0455 0527 68
0556 0628 0528 0600 90

Lamp off L1 G150 N375 K 2.17 0629-0638

###L1G150_N180K 2.17 Ne,Ar,Xe
###L2G040 AO N180J 1.3 Ar

LUCI1 LUCI2 EL Comments:___5sec exposures, loaded 12 deg increment accidentally while working on other things________

0364 0731 0602 0693 90 FlexComp_Calib12.xml
0732 0822 0694 0784 68
0823 0913 0785 0875 46
0914 1004 0876 0966 24

Lamp off L1 G150 N1.8 K 2.17 1005-1014

darks and L1 G150 1as longslit flats

-- BarryRothberg - 02 Sep 2020

This topic: Commissioning > Main > WebHome > Com20200903
Topic revision: 03 Sep 2020, JenniferPower
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Foswiki? Send feedback