UT 15-December-2019
OSA: D.G.Huerta
ISp: G. Bechetti
Mtn Manager: T. Forsyth
ISA: B. Rothberg (Tucson)
AO: G. Taylor (Tucson)
Special Guest Stars: Team Arcetri (Italy), J. Christou (Tucson)
SOUL Commissioning
UT 00:23 - LUCIs ready, test dakrs taken:
L1 0001-0002 2.51 sec dark
L2 0001-0002 2.51 sec dark
UT 00:24 - Configuring for closed dome testing with ARGOS cal unit
UT 04:14 - still closed - taking closed dome data for SOUL
UT 06:26 - fogged in, outside temp -2C, 99% humidity, question: is there ice forming on the building? is the building wet?
-telescope handed over from SOUL to ARGOS to LBTO/Eng (hot potato)
-no ice on telescope enclosure yet
UT 12:19 - still closed....
--
BarryRothberg - 15 Dec 2019