MODS1 Commissioning Run 4: UTC 2011 January 14-18
Observer(s): R. Pogge (OSU)
Telescope Operator: S. Allanson (LBTO)
Telescope Support: J. Little (LBTO)
Instrument Support: T. Shih (LBTO)
Summary
The enclosure bogie problem is very severe. After their engineering review this morning, I was informed that the telesope
could be disabled for up to 2 weeks while the problem is being addressed.
For the short term I will use the time to continue MODS1 off-sky testing. Having access to a live instrument provides an opportunity
to move various tests and observing command-and-control enhancements ahead on the schedule. I can't test some things back
home like I can here with a live MODS just 4 floors up.
We (LBTO and Team MODS) will be reviewing the commissioning plan going forward to see how we can still make our target of
SDT for late May/early June.
--
RichardPogge - 13 Jan 2011