AGw Commissioning for 29-30 September 2008 (Day 1)

Observers: Andrew (and Doug on call) J. Hill in Tucson
Software Support: N. Cushing, P, Grenz in Tucson
Telescope Operators: A. Ceranski

Summary

High Winds kept the Telescope closed all night.

Paul, Norm and John trouble positioning the tertiary mirror. Faults in the amplifier appeared to not position the tertiary in the correct position. (Paul, Norm, John, more information?)