Monday, March 9th, 2009: Doug's Work Log

  • In the morning we met our agent, got keys to the apartment, got instructions as to how to turn things on and off and checked the list of furninture
  • Arrived at the lab at 2:00 pm
  • Marco worked on his simulation routines
  • Remeasured with Marco, Runa and Armando the vertical clearance of the cooling pipes. Left the G-ring off so could more easily measure the relevant distances. Values were good, and several millimeters larger than Marco's simulations
  • In the evening:
    • Marco, Runa and Armando Mounted G-ring on dummy hub
    • Armando, Runa, Marco and Rick mounted the Secondary in the Solar Tower. They cabled DM672a to the through plate, and sealed the top of the tower.

-- DougMiller - 14 Mar 2009